Two proposals for the fourth line of Etesa

Posted on 2019-04-09

Electric Interconnection SAESP   of Colombia, and China Electric Power Equipment and Technology Co. Ltd.   of China, delivered technical and economic proposals for the design, construction, operation and transfer of the fourth electric transmission line.

 

The proposals were delivered between 8:00 am and 10:00 am and were attended by the manager of Etesa, Gilberto Ferrari and the energy secretary, Víctor Urrutia, among others.

 

The other three consortia that were prequalified did not arrive: Consorcio Chiriquí Transmisora ??de Energía (Spain), Four Seasons Consortium (India, France and Brazil), and Vasco Núñez de Balboa Transmission Consortium (Canada and Spain).

The commission must evaluate the technical proposals to verify that they comply.

The economic proposals are saved to be opened later next to the envelope of the Etesa reference price. 

 

Source LaPrensa